Schedule

Critical Path

DE: Kritischer Pfad

The longest sequence of activities determining minimum project duration.

Detailed Explanation

The critical path is the longest sequence of dependent activities determining the shortest possible project duration. Every project has at least one critical path; some have multiple paths of equal length.

Activities on the critical path have zero total float — any delay directly extends the project end date. This makes the critical path the primary focus for schedule management.

The critical path is not static — it can shift during execution as activities finish early or late. Experienced PMs also monitor near-critical paths (low float) as potential risk areas.

Key Points

  • Longest path = minimum project duration
  • Zero float on critical activities
  • Can have multiple critical paths simultaneously
  • Can shift during execution
  • Near-critical paths need monitoring too
  • Key input for crashing and fast-tracking

Practical Example

Product launch critical path: Market Research (3w) -> Product Design (6w) -> Manufacturing (8w) -> Quality Testing (2w) -> Distribution Setup (3w) = 22 weeks. Marketing prep (4w) runs parallel with 18 weeks of float. A 1-week manufacturing delay slips the entire launch by 1 week.

Tips for Learning and Applying

1

Assign your best resources to critical path activities

2

Build early warning indicators — do not wait for delays

3

Consider critical chain method as an alternative

4

Crash the critical path first — crashing non-critical activities is wasteful

Want to Master These Concepts?

Our courses cover all these terms in depth with practical examples and exercises.